Cranwood Project Progress Update

25/07/2025


Block A

  • Concrete frame completed up to Level 3; works progressing on Level 4.
  • External envelope: Light steel frame infill panels with cementitious board progressing to Level 1.
  • Windows installation underway at Level 0, followed by scaffold strike.
  • Bricklayers have commenced works below DPC.
  • Internally: 1st fix drylining and M&E ongoing on Lower Ground and Ground Floor.

Block B

  • External envelope complete, including full brickwork to roof level, windows, and balcony doors.
  • Internally: 2nd fix complete; taping and jointing now underway.
  • Roofing works in progress, including the mansard roof.

Block C

  • External envelope completed.
  • Scaffold removed from the rear elevation.
  • Landscaping works to commence.
  • Taping and jointing in progress.

A big thank you to all our suppliers and subcontractors for your continued hard work and commitment in bringing this project to life. Your efforts are truly appreciated.

Follow us for more updates as the Cranwood project continues to take shape.


Latest Updates.

At Formation, we value keeping our clients and followers updated on our journey. Stay informed with the latest news on new projects, client wins, team achievements, industry updates, charity events, community initiatives, and milestones as we work together toward success.

Services.

At Formation Design and Build Ltd, we offer a comprehensive range of construction services, backed by years of experience delivering high-quality projects. Our expertise spans residential construction, including affordable housing, as well as hotel developments, and student accommodation. We also provide mechanical and electrical (M&E) services, ensuring seamless integration of essential building systems. Additionally, our repairs and maintenance division ensures long-term asset performance and reliability. With a strong track record across these sectors, we are committed to delivering excellence, efficiency, and value on every project.